The Stanislaus County Board of Supervisors on Nov. 3 approved the reallocation of approximately $4.5 million in American Rescue Plan Act funding to support infrastructure construction at the Crows Landing Industrial Business Park.
The approved funding exchange shifts $4.5 million in ARPA funds from various county island community projects to the Crows Landing Industrial Business Park project while replacing those dollars with an equal amount from the project’s existing general fund allocation. County officials said the move allows the island projects to remain fully funded while providing greater flexibility for the business park infrastructure work.
County leaders said the funding adjustment will help advance infrastructure improvements at the former Crows Landing Air Facility, a 1,528-acre property envisioned as a future regional employment center for western Stanislaus County.
Originally commissioned in 1942 as an auxiliary airfield to Naval Air Station Alameda, the facility was identified for closure during the federal government’s Base Closure and Realignment Commission process in the 1990s. Congress transferred the property to Stanislaus County in 1999.
Since acquiring the site, county officials have pursued redevelopment plans aimed at creating sustainable-wage jobs and reducing the number of residents who commute outside the county for employment opportunities. The county adopted the Crows Landing Industrial Business Park Specific Plan in 2018.
At full build-out, a process expected to take 30 to 40 years, the development could include more than 14 million square feet of industrial and commercial space and a 370-acre public-use airport.
The first phase of development requires backbone infrastructure estimated to cost between $36 million and $42 million. Planned improvements include water and wastewater facilities, grading, drainage systems, utilities and road upgrades.
The county previously committed $20 million in general fund reserves to the project, including $4.2 million for design and engineering work. Officials also secured nearly $3.5 million in federal funding through the Environmental Protection Agency’s State and Tribal Assistance Grants program for potable water improvements and allocated $12 million in ARPA funding toward water infrastructure in 2023.
According to the latest quarterly project update, the business park remains in the construction phase. Current work includes installation of approximately 18,000 feet of dual 12-inch water pipeline along Fink Road connecting a well site to the development’s reservoir and pump station. Additional projects include construction of a 1.6-million-gallon water storage tank, a new pump station, electrical control building, emergency generator and related water system improvements.
County officials noted that a 2024 emergency well repair required the expenditure of $1.37 million in ARPA funds. Environmental clearance has been completed and construction is underway.
The quarterly report, presented to supervisors every August, November, February and May, tracks progress, costs and funding for both community infrastructure projects and the Crows Landing development. County staff said future recommendations on reallocating excess funding could be brought forward as construction continues and project costs become more defined.