For the first time since being constructed in 1954, homes along Rose Avenue in the Morrow Village subdivision are receiving curb, gutter and sidewalk.
The work is the second phase of a sidewalk construction project for Morrow Village, being funded by Community Development Block Grants and Measure L tax revenue.
The project consists of installing ADA compliant pedestrian sidewalk, driveway ramps, corner ramps, and curb and gutter on Rose Avenue from Garrison Road to Whitmore Avenue.
City Engineer Kevin Waugh said this is the second of five phases to bring modern standards to an older area of Ceres. Morrow Village is located north of Whitmore Avenue between Moffet and Mitchell Road.
Phase 1 was completed last year on Garrison Avenue from Moffet to Rose Avenue.
The third phase will bring sidewalks to the curvilinear section of Eloise Avenue between Garrison Avenue and Joy Avenue in 2024; while Phase 4 will improve Joy between Eloise and Rose in mid-summer in 2026.
The fifth and final section brings sidewalks to homes on Joy Avenue south of Eloise.
In April the Ceres City Council awarded the $445,827 construction contract to United Pavement Maintenance of Hughson. Construction support including but not limited to material testing is estimated to be $20,000, and a 10 percent contingency brings the project construction total to $512,410.